Attendees: Joan Salome-Rodriguez, Erica Eliason, Emily Ruby, Marlene Donnelly, Eymund Diegel, Aaron Kaufman, Katia Kelly, Richard Lawrence, Susan Yung The Committee discussed the following: 1. Aaron Kaufman alerted us to the closure of a sewage outflow (unlicensed) at the 3rd Street Bridge (south side) on the Gowanus Canal. Appears it comes out of the concrete mixing facility…. Read more »
Committee: CSOs
July 23, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal
In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris and for grout placement between the armor mats is ongoing. Work began on May 9th and is anticipated to be completed in the next day or two. The flushing tunnel is tentatively scheduled to be reactivated for 24 hours this Wednesday, July 24th,… Read more »
May 28, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal
In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris is ongoing Work began on May 9th Work is anticipated to be completed by the end of July Grouting of the armor mats in this area is being conducted concurrently as areas are dredged Carroll Street bridge – no updates, 65% design… Read more »
U.S. EPA Inspector General’s Report on the Audit of Gowanus Canal CSO Tanks
The Office of the Inspector General (OIG) of the United States Environmental Protection Agency (EPA) last week issued its report on an audit it conducted of the timing of the construction of the combined sewer overflow (CSO) tanks required by the EPA as part of the Gowanus Canal Superfund remedy. The OIG undertook the audit… Read more »
Update on the Status of Gowanus Canal Superfund Cleanup
USEPA Region 2 provided us with the following update on the status of the Gowanus Canal Superfund cleanup on February 27 (edited slightly for elucidation). In-Canal Work Remedial Target Area (RTA) 1 (Top of the canal to 3rd Street) The Potentially Responsible Parties (PRPs) are currently laying down the armor mat layer in the canal…. Read more »
Gowanus Canal Combined Sewer Overflow Facility Construction Notice: Sidewalk and Lane Closures
The New York City Department of Environmental Protection issued the following notice on May 11th regarding sidewalk and lane closures around the site of the large sewage-retention tank being constructed at the head end of the Gowanus Canal: The New York City Department of Environmental Protection is constructing an 8-million-gallon underground tank to intercept and… Read more »
NYC DEP Public Engagement Meeting on Gowanus Canal “Owls Head” CSO Facility, Thursday, March 16, 7:00 p.m.
On Thursday, March 16, 2023, at 7 p.m., the New York City Department of Environmental Protection (DEP) will host another public-engagement meeting about the development of the Gowanus Canal “Owls Head” combined-sewer overflow facility planned for 2nd Avenue and 6th Street in Brooklyn. DEP and the design team will report back on the feedback received… Read more »
NYC DEP Public Engagement Meeting on Gowanus Canal “Owls Head” CSO Facility, Wednesday, October 26, 7:00 p.m.
On Wednesday, October 26, 2022, at 7 p.m., the New York City Department of Environmental Protection (DEP) will host its third public-engagement meeting about the development of the Gowanus Canal “Owls Head” combined-sewer overflow facility planned for 2nd Avenue and 6th Street in Brooklyn. DEP and the design team will report back on the feedback… Read more »
NYC DEP Public Engagement Meeting on Gowanus Canal “Owls Head” CSO Facility, Thursday, May 12, 7:00 p.m.
On Thursday, May 12, 2022, at 7 p.m., the New York City Department of Environmental Protection (DEP) will host another online public-engagement meeting about the development of the Gowanus Canal “Owls Head” combined-sewer overflow facility planned for 2nd Avenue and 6th Street in Brooklyn. DEP and the design team will report back on the feedback… Read more »
Gowanus Canal Community Advisory Group Resolution Requesting NYCDEP Cooperation with EPA Mandates on Sewer Separation
At its February 22, 2022 general meeting, the Gowanus Canal Community Advisory Group passed the following resolution initiated by the Water Quality/Technical Committee requesting that the New York City Department of Environmental Protection cooperate with US Environmental Protection Agency mandates regarding sewer-separation projects. The resolution reads as follows: Re: Requesting NYC Department of Environmental Protection… Read more »