May 28, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal

Posted by & filed under CSOs, EPA Updates, Frontpage, Remediation Work.

In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris is ongoing Work began on May 9th Work is anticipated to be completed by the end of July Grouting of the armor mats in this area is being conducted concurrently as areas are dredged Carroll Street bridge – no updates, 65% design… Read more »

NYS DEC Community Update, September 2023

Posted by & filed under Fact Sheets, Frontpage, NYS DEC, Remediation Work, Upland Sites.

The New York State Department of Environmental Conservation has issued a new community update regarding Brownfield and State Superfund cleanup activities around the Gowanus Canal. The update includes information on a public availability session that NYS DEC and the NYS Department of Health will hold on the evening of October 3rd, and details on plans… Read more »