Please join us for our July 2024 General Meeting, on Tuesday, July 23, from 6:30 p.m. to 8:30 p.m., conducted via Zoom video conference. In order to join the meeting, you must pre-register, here: https://usepa.zoomgov.com/meeting/register/vJIsdeusrjkvGeNZXWh8T9KUHNlpP4-pw7w DRAFT AGENDA (all times are approximate) 6:30 – 6:45 p.m.: Welcome and CAG Member Introductions 6:45 – 7:45 p.m.: EPA Updates… Read more »

June 25, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal

Posted by & filed under EPA Updates, Frontpage, Remediation Work, Upland Sites.

In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris is ongoing Work began on May 9th Work is anticipated to be completed by the end of July which will allow for reactivation of the Flushing Tunnel NAPL was discovered in the Flushing Tunnel, but the source is uncertain The Trust is… Read more »

Minutes of the June 3, 2024 Meeting of the Gowanus Canal CAG Water Quality/Technical Committee

Posted by & filed under Committee Meetings, Frontpage, LTCP, Water Quality & Technical.

Attendees: Joan Salome-Rodriguez, Eymund Diegel, Richard Lawrence, Joseph Alexiou, Louis Kleinman, Erica Eliason, Aaron Kaufman The Committee discussed the following: 1. Water Quality will begin to review materials in order to prepare written comments related to the below public notice from DEC: Public Notice Advanced Notice of Proposed Rule Making – NYS Triennial Review of Water… Read more »

Gowanus Canal Community Advisory Group Comments on the Gowanus Canal Natural Resources Damage Assessment Plan

Posted by & filed under Frontpage, Natural Resource Damage Assessment.

On May 29, 2024, the Gowanus Canal Community Advisory Group submitted the following comments to the New York State Department of Environmental Conservation on the Gowanus Canal Natural Resources Damage Assessment Plan that was released on March 1, 2024. You can read our response below, or click here to view and download a PDF of… Read more »

May 28, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal

Posted by & filed under CSOs, EPA Updates, Frontpage, Remediation Work.

In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris is ongoing Work began on May 9th Work is anticipated to be completed by the end of July Grouting of the armor mats in this area is being conducted concurrently as areas are dredged Carroll Street bridge – no updates, 65% design… Read more »

U.S. EPA Inspector General’s Report on the Audit of Gowanus Canal CSO Tanks

Posted by & filed under CSOs, EPA Updates, Frontpage, Sewers.

The Office of the Inspector General (OIG) of the United States Environmental Protection Agency (EPA) last week issued its report on an audit it conducted of the timing of the construction of the combined sewer overflow (CSO) tanks required by the EPA as part of the Gowanus Canal Superfund remedy. The OIG undertook the audit… Read more »

Minutes of the March 14, 2023 Meeting of the Gowanus Canal CAG Administrative Committee

Posted by & filed under Admin, Committee Meetings, Frontpage.

The Admin Committee met via zoom on March 14th to review two new applications for membership in the CAG. The applicants are Daniel Pecoraro and Donald Minerva. The Admin Committee voted unanimously to send Daniel Pecoraro’s application forward so that he can be interviewed by the full CAG at a general meeting. The Admin Committee also decided to contact Donald Minerva to… Read more »

Trustees Release Draft Natural Resource Damage Assessment Plan for Gowanus Canal Superfund Site

Posted by & filed under Frontpage, Natural Resource Damage Assessment, NYS DEC.

Public Comment Period Runs Until April 15, 2024 The Gowanus Canal Natural Resource Damage Assessment Trustee Council, comprised of the National Oceanic and Atmospheric Administration (NOAA), New York State Department of Environmental Conservation (NYSDEC), and the United States Department of the Interior’s U.S. Fish and Wildlife Service (USFWS), have released the draft Natural Resource Damage… Read more »

Update on the Status of Gowanus Canal Superfund Cleanup

Posted by & filed under CSOs, EPA Updates, Frontpage, Remediation Work.

USEPA Region 2 provided us with the following update on the status of the Gowanus Canal Superfund cleanup on February 27 (edited slightly for elucidation). In-Canal Work Remedial Target Area (RTA) 1 (Top of the canal to 3rd Street) The Potentially Responsible Parties (PRPs) are currently laying down the armor mat layer in the canal…. Read more »

USEPA Region 2 Response to Gowanus Canal CAG’s October 2023 Resolution Concerning Access to Parcel 4 of the former Citizens MGP Site

Posted by & filed under Frontpage, Land Use, Remediation Work, Upland Sites.

On January 23, 2024, Pat Evangelista, Director of EPA Region 2’s Superfund and Emergency Management Division, sent the letter posted below in response to a resolution passed by the Gowanus Canal Community Advisory Group at its October 24, 2023 general meeting, which asked the EPA to assume responsibility for remediating the entirety of the former… Read more »