Minutes of the September 10, 2024 Meeting of the Gowanus Canal CAG Land Use Committee

Posted by & filed under Committee Meetings, Frontpage, Land Use, Manufactured Gas Plants, Remediation Work, Upland Sites.

Attendees:  (listed in order of appearance) CAG Members: Andrea Parker, Hildegaard Link, Erica Eliason, Peter Reich, Linda LaViolette, Joan Salome-Rodriguez, Susan Yung, Lisa Bowstead, Louis Kleinman Guests: Brian Carr, Alex Gregor, Oscar Fock, Terri Thomson, Aaron Kaufman Here’s a link to the video recording of the meeting: https://drive.google.com/drive/folders/1-tVj203tQ1gliRFYINLCmkXwDKJfrJ3f Briefly, the committee discussed the following (please listen… Read more »

July 23, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal

Posted by & filed under CSOs, EPA Updates, Frontpage, Remediation Work, Upland Sites.

In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris and for grout placement between the armor mats is ongoing. Work began on May 9th and is anticipated to be completed in the next day or two. The flushing tunnel is tentatively scheduled to be reactivated for 24 hours this Wednesday, July 24th,… Read more »

June 25, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal

Posted by & filed under EPA Updates, Frontpage, Remediation Work, Upland Sites.

In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris is ongoing Work began on May 9th Work is anticipated to be completed by the end of July which will allow for reactivation of the Flushing Tunnel NAPL was discovered in the Flushing Tunnel, but the source is uncertain The Trust is… Read more »

May 28, 2024 Update from EPA Region 2 on the Status of Work In and Around the Gowanus Canal

Posted by & filed under CSOs, EPA Updates, Frontpage, Remediation Work.

In-Canal Update Supplemental dredging near the flushing tunnel to remove recently deposited debris is ongoing Work began on May 9th Work is anticipated to be completed by the end of July Grouting of the armor mats in this area is being conducted concurrently as areas are dredged Carroll Street bridge – no updates, 65% design… Read more »

Update on the Status of Gowanus Canal Superfund Cleanup

Posted by & filed under CSOs, EPA Updates, Frontpage, Remediation Work.

USEPA Region 2 provided us with the following update on the status of the Gowanus Canal Superfund cleanup on February 27 (edited slightly for elucidation). In-Canal Work Remedial Target Area (RTA) 1 (Top of the canal to 3rd Street) The Potentially Responsible Parties (PRPs) are currently laying down the armor mat layer in the canal…. Read more »

USEPA Region 2 Response to Gowanus Canal CAG’s October 2023 Resolution Concerning Access to Parcel 4 of the former Citizens MGP Site

Posted by & filed under Frontpage, Land Use, Remediation Work, Upland Sites.

On January 23, 2024, Pat Evangelista, Director of EPA Region 2’s Superfund and Emergency Management Division, sent the letter posted below in response to a resolution passed by the Gowanus Canal Community Advisory Group at its October 24, 2023 general meeting, which asked the EPA to assume responsibility for remediating the entirety of the former… Read more »

Community Forum on the Gowanus Brownfields Cleanup, Thursday, January 25, 6 p.m.

Posted by & filed under EPA Updates, Frontpage, NYS DEC, Public Meeting, Remediation Work, Upland Sites.

Assembly Member Jo Anne Simon, in partnership with the offices of Representative Dan Goldman, Senator Andrew Gounardes, and Council Member Shahana Hanif, will host a community forum with the New York State Department of Environmental Conservation (DEC), New York State Department of Health (DOH), and the Environmental Protection Agency (EPA) on the ongoing Brownfields Project…. Read more »

Gowanus Canal Community Advisory Group Resolution Asks EPA to Include Former Citizens Manufactured Gas Plant Site within Purview of Gowanus Superfund Cleanup

Posted by & filed under Frontpage, Land Use, Remediation Work, Resolutions, Upland Sites.

At its October 24, 2023 general meeting, the Gowanus Canal Community Advisory Group passed the following resolution, initiated by the Land Use Committee, asking U.S. EPA Region 2 to assume responsibility for remediating the entirety of the former Citizens Manufactured Gas Plant site under the auspices of the Gowanus Superfund cleanup, due to the ongoing… Read more »

NYS DEC Public Availability Session, Tuesday, October 3, 7:00 p.m.

Posted by & filed under Frontpage, NYS DEC, Public Meeting, Remediation Work, Upland Sites.

The New York State Department of Environmental Conservation has scheduled a community availability session on Tuesday, October 3, 2023 from 7:00 p.m. to 9:00 p.m. at PS 372, 512 Carroll Street, Brooklyn, NY 11215, at which it will discuss the community-wide investigation and cleanup activities planned for Brownfield sites in the Gowanus area. You can… Read more »

NYS DEC Community Update, September 2023

Posted by & filed under Fact Sheets, Frontpage, NYS DEC, Remediation Work, Upland Sites.

The New York State Department of Environmental Conservation has issued a new community update regarding Brownfield and State Superfund cleanup activities around the Gowanus Canal. The update includes information on a public availability session that NYS DEC and the NYS Department of Health will hold on the evening of October 3rd, and details on plans… Read more »